The foreign matter and metal debris on the machine tool and mold should be removed every day when the CNC bus bending machine is started. Check whether the mold is firmly installed, whether the electrical switches, cables, and fasteners are normal and loose. Before machine tool maintenance or machine cleaning, the upper mold should be aligned with the lower mold and then put down and shut down until the work is completed. If it is necessary to start the machine or other operations, the mode should be selected in manual and ensure safety. The maintenance content of the following aspects is summarized as follows:
Hydraulic oil circuit
(1) Lubricate each point according to the lubrication requirements every day;
(2) Lubricate the ball screw and rolling guide every day after cleaning;
(3) Before working every day, wipe off the residue on the mold;
(4) Regularly clean the filter screen of the oil outlet filter;
(5) Regularly check the oil tank of the air-liquid pump, replace it after one month of first use, and replace the oil every year according to the specific situation, and the minimum oil temperature should not be lower than 10°C;
(6) Check the oil level of the fuel tank every week. If the hydraulic system is repaired, it should also be checked. If the oil level is lower than the oil window, hydraulic oil should be filled;
(7) When adding YB-N46 hydraulic oil into the oil tank, it must be filtered more than five times with an oil filter below 10 mesh. The oil tank can only be refueled after it is cleaned, and the depth is within the range of the oil tank gauge.
Filter
(1) The filter should be replaced or thoroughly cleaned every time the oil is changed;
(2) If the machine tool has related alarms or other filter abnormalities such as dirty oil quality, it should be replaced;
(3) The air filter on the fuel tank should be checked and cleaned every 3 months, preferably replaced every 1 year.
Hydraulic components
(1) Clean hydraulic components (substrates, valves, motors, pumps, oil pipes, etc.) every month to prevent dirt from entering the system, and cleaning agents cannot be used;
(2) After the new machine has been used for one month, check whether there is any deformation at the bends of the oil pipes. If there is any abnormality, it should be replaced. After two months of use, the connections of all accessories should be tightened. stress free.
Lubrication part
Check the lubrication of guide rails, bearings, screw rods, chains and all moving and transmission parts to ensure they are clean, rust-free and adequately lubricated (replace lubricating oil if necessary). Check and unclog the grease nipple and lines to make sure they are working properly.
Mechanical part
Check whether the movement of each transmission part is normal and the wear condition, and the bolt fastening condition of each key part.
Electrical parts
Turn off the power, clean the electrical cabinet, wipe the surface of the motor, arrange the wires in the cabinet, make the wire slots neat and beautiful, and there is no debris in the cabinet, remove the dust in the cabinet, check the working status of the exhaust fan and motor fan, and ensure their good work . Replace damaged switches, buttons, indicator lights and instruments, etc.
Machine surface
Scrub the outer surface of the machine and check the various safety devices of the equipment to ensure that they are effective and there is no missing.